University of Notre Dame- Prinderville Hall

Prinderville Hall Stage 2 Fit Out

Project Description

AWB was awarded the contract to deliver internal fit-out works at Prindiville Hall for the University of Notre Dame. The project aimed to modernise and reconfigure the internal space to support enhanced functionality and comfort for university operations. AWB successfully delivered a high-quality, fully integrated interior environment tailored to the client’s specifications, with all works completed on time, on budget, and in coordination with site requirements.

Scope Summary

  • AWB commenced works in December 2022, beginning with demolition and waste removal, including asbestos-containing material (ACM) removal. The scope included installation of new ceilings, skylights, partitions, doors, windows, and custom joinery. Interior finishes were upgraded with new floor coverings, painting, and installation of fixtures and fittings.
  • Comprehensive services were delivered across plumbing and hydraulics, electrical (including lighting, communications, and security), mechanical systems, and dry fire protection including emergency and smoke detection systems. All works were completed over a 5-month period with zero lost time injuries (LTIs), and in full alignment with the University of Notre Dame’s expectations

Key Deliverables

Design & Scope Development

Collaborating with architects, consultants, and clients to define project requirements, layouts, and specifications.

Site Supervision & Project Management

End-to-end coordination of trades, timelines, safety, and quality across all phases of the project.

Stakeholder & Client Communication

Transparent and proactive engagement with clients, consultants, and government bodies through regular updates and reporting.

Compliance & Certification Management

Ensuring all works meet relevant codes and standards, including WHS, Access Aus (AS 1428), and environmental regulations.

Safety Planning & Risk Management

Development and implementation of SWMS, risk assessments, and protocols for high-risk activities such as working at heights and asbestos removal.

Subcontractor Coordination

Engaging and managing licensed trades and specialists, including asbestos removalists, concreters, roofers, and civil contractors.

Final Clearance & Occupancy Certification

Coordination with Licensed Asbestos Assessors and Occupational Hygienists to obtain clearance certificates and occupancy permits before re-entry.