Project Description
AWB was awarded the contract to deliver accessible ramp upgrades and an ACROD parking bay at Gingin District High School, engaged by Spotless Facility Services. The project aimed to improve accessibility and compliance with disability access standards across key areas of the school. AWB successfully delivered safe, functional, and regulation-compliant infrastructure tailored to site requirements, with all works completed to specification and in coordination with the client’s representative.
Scope Summary
- AWB constructed new accessible ramps in two designated areas and installed an ACROD-compliant car parking bay. The scope included earthworks, concrete paving and kerbing, bitumen surfacing, line marking, and installation of handrails. Additional works involved excavation and backfill, compaction of base course material, drainage, piping installation, landscaping, reticulation relocation, and termite protection.
- All works were completed under strict noise control standards to minimize disruption to school operations. The project was delivered over a 16-week period, on time and on budget, with zero lost time injuries (LTIs) and full alignment with Spotless Facility Services’ expectations
Key Deliverables
Transparent and proactive engagement with clients, consultants, and government bodies through regular updates and reporting.
Development and implementation of SWMS, risk assessments, and protocols for high-risk activities such as working at heights and asbestos removal.
Engaging and managing licensed trades and specialists, including asbestos removalists, concreters, roofers, and civil contractors.
Delivering works in operational schools, hospitals, offices, and public spaces with minimal disruption to occupants and services.
Dust suppression, noise mitigation, waste management, and secure site access to protect people and property.
Coordination with Licensed Asbestos Assessors and Occupational Hygienists to obtain clearance certificates and occupancy permits before re-entry.
Final inspections, punch list resolution, and delivery of completion documentation including warranties and maintenance guidance.
Project Overview
CUSTOMER
Programmed FM
PROJECT VALUE
$400k -$500k
YEAR COMPLETED
January , 2017